TRADE TOOLS
Language
Units
Share:
Slab dimensions
Slab results
Volume needed
cubic yards
Bags needed
60 lb bags
Ready-mix trucks
at 8 cu yd per truck
Slab area
sq ft
Footing dimensions
Footing results
Volume needed
cubic yards
Bags needed
60 lb bags
Per footing
bags each
Volume (cu ft)
cubic feet total
Column / post hole dimensions
Column results
Total volume
cubic feet
Total bags
60 lb bags
Per column
bags each
Per column vol
cu ft each
Mix ratio calculator

Results are for guidance only. Always verify with a qualified professional. Disclaimer

Mix results
Cement Sand Aggregate
Cement
kg needed
Sand
kg needed
Aggregate
kg needed
Water (w/c 0.5)
litres
Quick reference

Slab thickness guide

Foot paths & patios: 4" (100mm) · Residential driveways: 4"–6" · Garage floors: 4"–6" · Commercial driveways: 6"–8" · Structural slabs: engineer-specified. Always place on compacted, well-drained base.

When to use bags vs ready-mix

Under 1 cu yd (27 cu ft): buy bags — more economical, mix on site. 1–3 cu yd: borderline — consider mini-mix delivery. Over 3 cu yd: order ready-mix truck. Large pours must be completed quickly before concrete sets.

Mix strength guide

C10 (1:3:6) — lean fill, mass concrete · C20 (1:2:4) — general use, slabs, footings · C25 (1:1.5:3) — beams, columns, reinforced · C30 (1:1:2) — high-load structural. Consult engineer for structural work.

Bag yields (approx)

40 lb bag: 0.30 cu ft · 60 lb bag: 0.45 cu ft · 80 lb bag: 0.60 cu ft · 1 cu yd = 27 cu ft = 45–90 bags depending on size. Always buy 10% extra.

Curing time

Initial set: 2–4 hours · Walkable: 24 hours · Drive on: 7 days · Full strength (28-day cure): 28 days. Keep moist for first 7 days. Do not pour below 5°C / 40°F without cold-weather precautions.

Concrete Calculator — Slabs, Footings & Bags Needed

Free tool · Works offline · Metric & imperial · Bags or ready-mix

How to calculate how much concrete you need

Concrete volume is simply length × width × depth. The tricky part is converting between units and accounting for waste. A 10×10 ft slab at 4" depth is 10 × 10 × (4/12) = 33.3 cubic feet = 1.23 cubic yards. Always add 5–10% for waste — formwork is never perfectly square, and you always lose some on the ground. This calculator handles the conversion automatically and tells you exactly how many bags to buy or whether ready-mix makes more sense.

How many bags of concrete for a 10×10 slab?

A 10×10 ft (3×3 m) slab at 4" (100mm) depth needs about 1.3 cubic yards (1 m³) of concrete. That's approximately:

For anything over 1 cubic yard (27 cubic feet), ready-mix is usually more economical — mixing that many bags by hand is exhausting and the result is less consistent. Use bags for small repairs, fence posts, and pours under 0.5 m³.

How thick should a concrete slab be?

Slab thickness depends on what it carries. Patios and paths: 75–100mm (3–4") is standard for foot traffic. Garage floors: 100–150mm (4–6") to handle vehicle weight — go to 150mm if you park heavy vehicles or store machinery. Driveways: 100mm (4") minimum, 150mm for heavy vehicles. Structural slabs with rebar: consult an engineer — typically 150–250mm depending on loads and span.

What concrete mix should I use?

For most residential work, a C20 mix (1:2:4 cement:sand:aggregate) is standard — suitable for slabs, paths, steps and non-structural footings. Use C25 (1:1.5:3) for garage floors, driveways and lightly reinforced elements. C30 (1:1:2) for structural beams, columns and anything an engineer has specified. Bagged products like Quikrete General Purpose are typically equivalent to C20–C25 — check the bag for compressive strength (usually 4000 psi / 27 MPa at 28 days).

Ready-mix vs bagged concrete — which is cheaper?

Bagged concrete costs roughly £5–8 per 25kg bag (covering about 0.015 m³). Ready-mix is typically £90–130 per m³ delivered. The crossover point is around 0.5–1 m³ — below that, bags are cheaper and more convenient. Above 1 m³, ready-mix saves time, money and back pain. Note that ready-mix has a minimum order (usually 1–2 m³) and needs to be poured quickly — have your formwork ready before the truck arrives.

Frequently asked questions

How many bags of concrete for fence posts?

A standard 100mm diameter fence post hole at 600mm deep needs about 0.005 m³ — roughly one 25kg bag per post. For larger posts or deeper holes use the column tab in the calculator.

How much does a yard of concrete cover?

One cubic yard (0.76 m³) covers 81 sq ft at 4" depth, or 54 sq ft at 6" depth. In metric: 1 m³ covers 10 m² at 100mm or 6.7 m² at 150mm.

How long does concrete take to cure?

Initial set: 24–48 hours (keep off it). Walking strength: 3–7 days. Full strength: 28 days. Keep concrete moist for the first 7 days — cover with plastic sheeting or damp burlap to prevent cracking.

Do I need rebar in a concrete slab?

For slabs over 3m span, vehicle traffic, or anywhere there's risk of settlement, yes. Use 10mm rebar at 300mm centres for a standard garage floor. Always check local building codes.